Combined cycle pipe rack modules loaded on a barge to be shipped down around the panhandle of Florida, up the East Coast, and up the Delaware River for Dominion Energy.

Here are a few facts about this project:

2 - 650 Megawatt blocks

Assembly duration - 5 months

PF, IW, OPTR - 100,000 manhours

13,500 tons combined

12,875 linear feet of pipe

100% Xray P-91 welds

1500 butt welds

1500 socket welds

1140 hangers

494 valves

7800 feet of insulation

No loss time accidents