Combined cycle pipe rack modules loaded on a barge to be shipped down around the panhandle of Florida, up the East Coast, and up the Delaware River for Dominion Energy.
Here are a few facts about this project:
2 - 650 Megawatt blocks
Assembly duration - 5 months
PF, IW, OPTR - 100,000 manhours
13,500 tons combined
12,875 linear feet of pipe
100% Xray P-91 welds
1500 butt welds
1500 socket welds
1140 hangers
494 valves
7800 feet of insulation
No loss time accidents